Frazier Park Public Utility District Meter Replacement Project and Emergency Replacement Well and Water Supply Project
Project Overview
The Frazier Park Public Utility District, with the help of Self-Help Enterprises, submitted an application to the State and obtained grant funding in order to replace water meters with smart meters, and replace a failing well (Well #5).
The application was approved and the State Water Resources Control Board has funded the project in the amount of $3,997,427.00.
The Replacement Well
The replacement for Well #5 (Well #7) was drilled and completed in early 2023. Due to low yield and poor water quality the new well was not a sucess. The well was filled and abandoned.
The Smart Meters
All residential meters have been replaced with smart meters.